Notice Regarding the Operation of Domestic Plants (As of July 7)

Jul. 07, 2025
DAIHATSU MOTOR CO., LTD.

DAIHATSU MOTOR CO., LTD. has decided to resume operations at the Daihatsu Motor Kyushu Co., Ltd. Oita (Nakatsu) Plant No.2 which had been temporarily suspended, as we have established a prospect for parts supply from suppliers.
Daihatsu offers its sincerest apologies for the worry this announcement will cause to our customers and other parties.

Plant Daihatsu Motor Kyushu Co., Ltd. Oita (Nakatsu) Plant No.2
Date Operations will resume from July 14, 2025
(All suspension dates: July 7-11, 2025 5 days in total (10 shifts ))
Products Model Mira e:S/PIXIS EPOCH/PLEO PLUS, TAFT, MOVE/STELLA, MOVE CANBUS

As of July 14, the only plants that are temporarily suspended are the Shiga (Ryuo) Plant 2nd District*1、2.

*1 Suspension dates: July 8-18, 2025 (a total of 9 days, 17 shifts).
*2 Operations will be suspended from the night shift on July 8.