Jul. 03, 2025
DAIHATSU MOTOR CO., LTD.
DAIHATSU MOTOR CO., LTD. will temporarily suspend production at the following vehicle production line due to a shortage of parts supply from suppliers.
Daihatsu offers its sincerest apologies for the worry this announcement will cause to our customers and other parties.
Plant | Shiga (Ryuo) Plant 2nd District |
---|---|
Date | July 14-18, 2025 5 days in total (10 shifts ) (All suspension dates: July 8*1-18, 2025 9 days in total (17 shifts )) |
Products Model | Rocky/Raize/REX, Tanto/Chiffon |
The operation of Daihatsu Kyushu Co., Ltd. Oita (Nakatsu) Plant No. 2*2 will be announced after a separate decision. Other plants will be in operation.
*1 Operations will be suspended from the night shift on July 8.
*2 Suspension dates: July 7-11, 2025 (a total of 5 days, 10 shifts).