Daihatsu Motor Co., Ltd. has made decision regarding the operation of domestic vehicle production line due to a shortage of parts from supplies.
Daihatsu offers its sincerest apologies for the worry this announcement will cause to our customers and other parties.
| Plant | Shiga (Ryuo) Plant No.2 | 
|---|---|
| Operating Date | April 4, April 7, 2025 2 days in total | 
| Suspension Date | April 2-3, 2025   2 days in total (All date: March 10-19, 24-26, 31-April 3 16days in total (30 shifts *)  | 
        
| Products Model | Rocky / Raize / REX, Tanto / Chiffon | 
| Plant | Kyoto (Oyamazaki) Plant | 
|---|---|
| Operating Date | April 4, April 7, 2025 2 days in total | 
| Suspension Date | April 2-3, 2025   2 days in total (All date: March 10-19, 24-26, 31-April 3 16days in total (30 shifts *)  | 
        
| Products Model | Probox, Thor/Roomy/Justy | 
| Plant | Head (Ikeda) Plant (Copen Factory) | 
|---|---|
| Operating Date | April 2-7, 2025 4 days in total | 
| Suspension Date | No (All date: March 19, 24-26 4 days in total (4 shifts )  | 
        
| Products Model | Copen (Daihatsu) / Copen (Toyota) | 
* Including cancellation of holiday work scheduled for Saturday, March 15.
Other plants will be in operation.