Regarding Production in Japan

Apr. 13, 2011

Daihatsu Motor (DMC) has decided production operation schedule of DMC and Daihatsu Motor Kyushu after April 18 as below.

We will restart vehicle production at DMC Head (Ikeda) Plant and Kyoto Plant. As a result, all Daihatsu plants will resume the operations.

Since the production operations will be done confirming the conditions of in-stock parts and parts supply, production volume is planned to be approximately 50 percent of normal.

We will continue the operations between April 18 and 28 (27 at some plants). Afterwards, all production facilities will enter their annual spring holiday through May 5. A decision on post-holiday production will be made after assessing the parts supply situation.